12-hour long of 7 days dumsor schedule to start today May 10

0
Listen to Article

The 12-hour long 7 days dumsor in some parts of the Greater Accra region is expected to start today 10th May 2021 and expected to end on Monday 17th May 2021.

The schedule is to enable the newly constructed Pokuase Bulk Supply(BSP) to GRIDCo’s 330kV transmission line.

It could be recalled that ECG released the timetable for the load shedding which is supposed to take place in some part of Accra from 10th to the 17th of May,2021.

The load shedding was categorized into four groups namely; Group A, B, C and D with each group expected to have their light turned off from 6 am to 6 pm or from 6 pm to 6 am each day.

See also  US$4m NCA Scandal: 3rd Accused Denies Involvement

See the timetable below:

source:browngh.com